Motorists were overjoyed as a major link between New Ross and Kilkenny reopened yesterday after nine weeks being closed.
A major restoration project’s been underway on the Ferrymountgarrett Bridge, which included repairs to the steel deck and concrete spans while the historic structure was also sandblasted and repainted.
Project manager Martin Fitzgerald says the complex works were completed a day ahead of schedule (as we reported yesterday), allowing traffic to return across the bridge.
For the next month a traffic management system will be in place to allow for the safe completion of concrete and parapet repairs on the bridge, as well as the installation of public lighting.
KCLR News’ Martin Quilty stopped by as the bridge was reopened yesterday evening – stay tuned to hear from those he met on our main morning News at 9am, lunchtime News at 1pm & evening News at 5pm. (Or click back to this page later to hear the recordings).